Project Update

August 21, 2024

General Note on Project Timeline and Corrective Actions:

 

We appreciate your patience as we strive to ensure that our project meets all requirements for full delivery. We are currently addressing some corrective items as well as additional schedule shifts due to rain days earlier this month.

 

We are fully engaged with the contractor to ensure that all of our delivery items for this project are complete.

 

We take pride in making certain that the full scope of work and budgeted items are accounted for, and if changes are made, that we do so in a fiscally, environmentally, and public friendly manner. Your patience and understanding are appreciated and we will have an update to our project estimated completion date posted soon. 

 

PLANNED UPCOMING ACTIVITIES:

 

  • Completing items to finalize project - please note that timeline shifted by several weeks due to contractor inefficiencies and inclement weather (rain) days in early August.

  • Corrective work:

    • Crack seal (complete)

    • Fog seal (complete)

    • Fog seal cleanup (week of August 20, 2024)

    • Valve adjustments (Southbound)

 

  • Remaining project items:

    • Complete tree installation

    • Complete median rock

    • Final roadway striping

    • Final signal installs/programming

 

 

Fog seal cleanup work, Bulverde Road, looking into Northbound lane

Awaiting striping and rock completion as part of project completion, Bulverde Road, facing North