Breeden Phase 1- West Russell Drainage Improvements Project
Breeden Phase 1- West Russell Drainage Improvements Project
The proposed project includes an underground drainage system to alleviate flooding issues associated with the lack of a drainage system. The proposed system will tie-in to an existing drainage system (6'X6' Single Box Culvert) on W. Ashby Place. The project was split into two phases; Phase 1A is N. Flores from W Ashby Place to W. Russell Place, and Phase 1B is W. Russell Place from N Flores to Breeden Ave.
Phase: 1A Complete/1B Complete
For more information: Call Public Works Storm Water Division at 210-207- 2799.
Estimated Construction Timeline: Winter 2022 - Fall 2023
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Budget:
1A Budget:
$1,090,000 (Storm Water Operating Fund)
$1,015,000 (General Fund)
$2,105,000 Total
1B Budget:
$1,840,000 (Storm Water Operating Fund)
Project Limits:
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: 210-207-3922, [email protected]
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.