Annie Area Interim Drainage Improvements
The resident at 219 Holland, as well as several residents along the 200 block of Annie Street are experiencing nuisance flooding stemming from the drainage easement located between 203 and 219 Holland...
Biering Ln. Interim Drainage Improvements
The residents of the Oakridge Pointe Neighborhood (a Planned Unit Development, or PUD) located on Brae Ridge Dr and backing up to Biering Road are experiencing nuisance flooding from Biering Road. ...
Blue Crest Drainage
1251 Blue Crest was platted without a drainage easement. Over the years, the property has been built up with fill. The easement upstream contains a 10' wide, 2' deep concrete flume...
Breeden Drainage Improvements: Phase 2 (Design Only)
The proposed project consists of storm sewer culverts and curb inlets along Breeden and side street intersections to capture the 25-year runoff. The Phase 2 storm system will tie into the 5x5 SBC trunkline...
Breeden Phase 1- West Russell Drainage Improvements Project
The proposed project includes an underground drainage system to alleviate flooding issues associated with the lack of a drainage system. The proposed system will tie-in to an existing drainage system (6'X6'...
Briarmall Drainage System
During heavy rainstorms, the Briarwick development is impacted due to two sources. The first is due to the upstream CPS property; this property drains towards the rear fence line of Briarwick properties...
Castleridge/Slick Ranch Floodplain Improvements
This project was previously funded for a Preliminary Engineering Report in FY 2014 due to massive flooding during the May 2013 floods. The report found that 451 properties ($39.3M) are in the 100-year...
Churchill Ave. Area Drainage Improvements
Development in Churchill Estates has filled in the existing drainage channel at several locations. In addition, there is no defined low to convey the storm water through the subdivision resulting...
Concepcion Creek Phase 1 Detention Pond(s)
More than 2,200 structures are now in harm’s way in the floodplain of the Concepcion Creek watershed. The Federal Emergency Management Agency is updating its floodplain map to add nearly 1,900 more...
Contessa Dr. Drainage Improvements
Citizens along Contessa Dr. have experienced flooding issues due to the street not having drainage capacity for the runoff flowing within the Right-of-Way. This project will add underground storm drainage...
Crestfield Area Drainage Improvements
Area residents have expressed concerns about nuisance flooding of streets within the neighborhood. There is an undersized drainage pipe on Crestfield Drive which causes water to back up onto the street....
D10 Drainage Improvements-Fox Run
The houses at 6303, 6300 and 6303 Fox Head are being impacted. This project will provide relief by intercepting the flow at the back fence line and channeling it underground between 6300 and 6303...
Jo Marie Area Drainage Improvements Phase 1
In 1975, site inspection by staff noted the area within the subdivision was flat with shallow swales that conveyed storm water from WW White Rd. to Jo Marie. The current drainage system on Jo Marie...
Menchaca St. Drainage Correction
Menchaca Street has been causing drainage issues for the residences along the Northside of the street. Water flows east along Menchaca towards NW28th St. but is also entering the properties along...
Michael Drainage Improvements
The resident at 262 Michael receives runoff from an adjacent drainage easement. The resident also reports ponding in the street. The channel beside this house has a dedicated drainage easement and is maintained...
Moss Brook Area Drainage
Several residents have expressed concerns about localized drainage issues, storm runoff entering their garages, and nuisance flooding on their properties. The proposed project will reconstruct the existing...
Orsinger Low Water Crossing
During storm events this area is a dangerous Low Water Crossing (LWC) with deep water. There have been 3 swift water rescues recorded within a 10 year period (2007-2017) at this location. This project...
Parham St. Drainage Improvements
This project will address multiple drainage issues concerning a partially constructed paper street. The proposed street reconstruction and drainage system will alleviate the issues and properly convey...
Pembroke Interim Drainage Improvements
The resident at 7110 Pembroke Rd. has expressed concerns of storm runoff entering her property from the city-owned drainage right-of-way located across from her residence. The city-owned drainage right-of-way...
Pinn Road Safety Improvements
Area residents, businesses, and motorists have expressed concerns about the Low Water Crossing (LWC) of mainstream Leon Creek at Pinn Rd and State Hwy 151. This crossing floods frequently under minor storm...
Riverwalk Gate 5 Replacement
Storm Water Operations staff monitors and controls water levels along the Riverwalk utilizing Gate 5 located Southwest quadrant of E. Nueva/Jack White intersection, which is maintained by Center City Development...
South Gevers St. Drainage Improvements Phase 1
This project will alleviate continuous drainage issues along S. Gevers and adjacent streets by installing an underground system along S. Gevers Street consisting of various pipe sizes and concrete boxes...
Thousand Oaks Erosion Protection
Concrete riprap under Thousand Oaks bridge is in disrepair and breaking off exposing the bluff which has led to extreme erosion in this area. Storm water runoff from two culverts combine east of Thousand...
Woller Road Interim Drainage Improvements
The residents of Hunter Chase and Woller Creek neighborhoods have reported ponding water and poor drainage along Woller Road. This project serves as an interim solution to the larger ponding issues on...
WW White/MLK Interim Drainage Improvements
There have been complaints of heavy flowing water on the west side of WW White Rd. at Martin Luther King Dr., specifically at the VIA bus stop north of the intersection. Pedestrians boarding the bus get...