2022-2027 Bond Project: Citywide Bridge Improvements LF
2022-2027 Bond Project: Citywide Bridge Improvements LF
The Bond Project will improve and rehabilitate existing deficient and deteriorated bridge structures and/or build new bridges within City limits within available funding.
Project Type: Streets, Bridges, & Sidewalks
Phase: Construction
Estimated Construction Timeline: Fall 2023 - Winter 2026
Project Contact: Joe Doctor - (210) 207-8415
Estimated Construction Timeline Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December).
Project Budget: | |
2022 General Obligation Bond (Streets) | $1,157,000.00 |
American Rescue Plan Act Funding (ARPA) | $3,800,000.00 |
Total | $4,957,000.00 |