Project Update: September 5, 2024
 

PLANNED UPCOMING ACTIVITIES:

  • 9/3/2024 - 9/6/2024:
    • ​JDA will continue drainage lateral construction System A at Jadestone
  • 8/26/2024 - 9/4/2024:
    • JDA will continue working on road excavation and grading and begin flexible base placement on the north side of the project from Babcock Road to Venado Trace
  • 8/26/2024 - 8/30/2024 
    • ATT to adjust ATT cable at Jadestone

                                                                                        

  • 8/26/2024 - 9/06/2024 
    • JDA will be working on road excavation and flex base placement on the north side of the project from Venado Trace to Oakland Road

 

                                                                                        

  • 8/26/2024 - 9/06/2024: 
    • JDA will be working on road excavation and flex base pavement on the north side of the project from Venado Trace to Oakland Road
  • 8/26/2024 - 9/06/2024:
    • ​Fox concrete will continue to work on curb wall, sidewalk, and driveways on the south side of the project
  • 8/26/2024 - 9/06/2024: 
    • JDA will be working on road excavation and flex base placement on the north side of the project

                                                                                        

  • 8/26/2024:
    • JDA installing drainage structure at Network and Prue Road

 

                                                                                    

  • 9/5/2024: 
    • Outfall C drainage continues from just south of Lockhill north toward Prue Rd.
    • Outfall C drainage continues between Verbena and Hollyhock.
  • 9/9/2024:
    • ​Lockhill closes to through traffic between Southwell and Oakland - for drainage construction. Detour via Prue Rd or Hollyhock.

                                                                                    

NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.

Business Outreach Specialist: 210-207-3922, [email protected]


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.


 

Question title

To receive project updates and details on future public meetings, please provide the following information.

Question title

Please share any feedback or questions about this project.

 

Excavation work continues on the north side of Prue Rd. looking West.

 

 

Excavation work and Box Culvert installs continue on the north side of Prue Rd. looking West.

 

 