Project Update 5/3/24:

For the next two weeks, we can expect the following work to be performed:

  • Sidewalks and curbs are currently being worked on and should be completed within the next 2 – 3 weeks weather permitting.
  • Topsoil, grass and mailboxes are scheduled to be reinstalled towards the last week of May or first week of June.

 

NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.

Business Outreach Specialist: 210-207-3922, [email protected]


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.

Question title

To receive project updates and details on future public meetings, please provide the following information.

Question title

Please share any feedback or questions about this project.

Storm Water Excavation and

Placing Pipe