2022-2027 Bond Project: Braun Road Sidewalks (Tezel Road to Northwest Loop 1604)
2022-2027 Bond Project: Braun Road Sidewalks (Tezel Road to Northwest Loop 1604)
The Bond Project will construct a shared-use path on northside of Braun Road from Tezel Road to Northwest Loop 1604 within available funding.
Project Type: Streets, Bridges, & Sidewalks
Phase: Design
Project Contact: Betsy Hove - (210) 207-7787
Estimated Construction Timeline: Summer 2025 - Fall 2026
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December).
Project Budget: | |
2022 General Obligation Bond (Streets) | $3,000,000.00 |
CPS Energy | $40,000.00 |
San Antonio Water System | $117,389.00 |
Total | $3,157,389.00 |
Project Limits:
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Project Presentation Documents
Proposed Improvements